top of page
ICL Group Project
Anvil Engineering completed the design for its new North American Blending operation at its plant in St. Louis, MO. in 2016. The building is a 45’ X 60’ X 60’ high chemical processing building constructed from structural steel and insulated metal panels (IMP’s). The facility was designed in a fast track nature in order to allow startup of the facility at the earliest possible timeframe.
PROJECT HIGHLIGHTS
​
-
Building designed to Class 2 Div 2 combustible dust standards
-
Structural as well as architectural design completed
-
Building process equipment design included: 8,000lb blender, packer, hoppers, sifters, screeners, and wrapper
-
Coordinated all MEP design and construction activities
1/4